The conversion of Lucky Electric Power Co. to locally sourced Thar coal may significantly improve the power plant’s dispatch and earnings while boosting returns for its sponsors, according to a report by Arif Habib Ltd.
The report said the expansion of Sindh Engro Coal Mining Co.‘s Thar Block-II mine to 11.2 million tons per year from the current 7.6 million tons would provide an additional 3.6 million tons of coal annually to LEPCL’s 660-megawatt power plant.
The additional coal supply is expected to enable LEPCL to fully switch from imported coal to Thar coal, potentially increasing the plant’s utilization to 60%-65% from about 37% currently, subject to electricity demand and transmission constraints, Arif Habib said.
SECMC was established in 2009 as a public-private partnership between the Sindh government and Engro and operates the 95.5-square-kilometer Thar Block-II coalfield. The Sindh government holds a 54.7% stake, while Engro and its affiliates own the remaining 45.3%.
The mine’s Phase I, with capacity of 3.8 million tons per year, commenced commercial operations in July 2019, while Phase II raised capacity to 7.6 million tons per year and achieved commercial operations in September 2022.
The Arif Habib report cited the latest National Electric Power Regulatory Authority merit order as showing a significant cost advantage for locally sourced Thar coal over imported coal. Thar-based plants have a specific generation cost of about Rs. 5.39-5.83 per kilowatt-hour, compared with Rs. 12.75/kWh for LEPCL when operating on imported coal, the report said.
The shift to Thar coal could therefore reduce LEPCL’s variable generation cost by about Rs. 6.9/kWh before transportation costs, materially improving its position in the merit order. “LEPCL’s shift to locally sourced Thar coal should materially improve its dispatch economics,” the report said.
The cost advantage is already reflected in plant utilization. Thar-based plants including EPTL, TEL, Thar Coal Block-I and ThalNova operated at roughly 70%-80% utilization in fiscal 2026, compared with 11% for CPHGC, 31% for Port Qasim and 36% for LEPCL, according to the report.
Arif Habib said LEPCL’s conversion should allow the plant to move higher in the merit order and increase dispatch, although north-south transmission constraints could continue to limit the evacuation of cheaper generation from southern Pakistan to northern load centers.
LEPCL’s regulated return
The conversion is also expected to increase LEPCL’s regulated return on equity to 29.5% from 27.2%, with the ROE per unit of electricity rising to Rs. 1.289 from Rs. 1.188, the report said. Based on Arif Habib’s estimates, the higher regulated return would generate an incremental Rs. 1.55 billion in ROE for LEPCL in fiscal 2027, rising to Rs. 1.80 billion by fiscal 2030.
For Lucky Cement Ltd., the benefit would translate into incremental earnings of Rs. 1.06-1.23 per share, according to the report.
LEPCL’s project cost was estimated at $956 million under NEPRA’s upfront tariff, financed through 75% debt of $717 million and 25% equity of $239 million. The higher ROE reflects additional returns allowed on the expanded project investment and is expected to provide a recurring earnings benefit rather than a one-time gain, Arif Habib said.
The Phase III expansion is also expected to materially increase SECMC’s return on equity. According to the report, SECMC’s ROE is projected to rise to Rs. 17.27 billion in fiscal 2027 from Rs. 11.45 billion, an increase of Rs. 5.82 billion or about 51%.
The incremental ROE is expected to reach Rs. 6.77 billion by fiscal 2030 as the expanded mine operates at higher capacity.
For Hub Power Co., or HUBCO, the additional ROE contribution is estimated at Rs. 465 million in fiscal 2027, rising to Rs. 541 million by fiscal 2030. That would translate into incremental earnings of Rs. 0.36-0.42 per share.
For Engro Holdings, the incremental ROE contribution is estimated at Rs. 692 million in fiscal 2027, increasing to Rs. 805 million by fiscal 2030, equivalent to Rs. 0.57-0.67 per share, according to the report. The expansion is supported by a coal supply agreement between SECMC and LEPCL and is expected to strengthen the economics of both the mining operation and the power plant by replacing expensive imported coal with cheaper domestic fuel.